Status of initiative: N/a
Description/achievement of initiative

The Government of Saint Lucia is partnering with Solar Head of State to install solar panels on the public residence of the Governor-General, Government House. This is part of the islandís target to generate 35% of its electricity from renewable sources by 2020 and 100% by 2030. This project will be a symbolic statement of intent by the government, and also a test project to encourage more future grid-connected solar projects on the island.

Implementation methodologies

Solar Head of State and its partners Free Island Energy and Noah Energy will install a rooftop grid-connected solar photovoltaic system using panels donated by Trina Solar and Inverters donated by Enphase Energy. Additional financial support was received from Sungevity and the California Clean Energy Fund.

Arrangements for Capacity-Building and Technology Transfer

The installation of this project will use a local installation company and some off-island experts will be brought in to provide training. Training in maintenance is also given to grounds staff of Government House. Local services have been used in every possible aspect of the project, and the training should increase capacity of installation crew for future projects.

Coordination mechanisms/governance structure

Solar Head of State (SHOS) is a non-profit coordinating the installation. Donations (financial and in-kind) are arranged by this organization and SHOS works with the Government of Saint Lucia to install the test project and ensure media focus.

Partner(s)

Government of Saint Lucia, Solar Head of State, Carbon War Room, Free Island Energy, Noah Energy, Sungevity
Deliverables
September 2016
Installation of solar panels on Government House, Saint Lucia
Resources devoted to implementation
Financing (in USD)
10,000 USD
Staff / Technical expertise
Installation services from Noah Energy and Free Island Energy
In-kind contribution
Panels from Trina Solar, Inverters from Enphase Energy
Staff / Technical expertise
Project management by Solar Head of State
Progress reports
Cut off date each year: 1 July
SMART
This initiative does not yet fulfil the SMART criteria.
PRIORITY AREASS
SDGs
Information
Location: Castries, Saint Lucia
Date of completion: October 2016
Operating in countries
Partner connections
Contact information/focal point(s)
James Ellsmoor, jellsmoor@solarheadofstate.org

Documents
#SIDSAction12595
Copyright 2016 United Nations Department of Economic and Social Affairs